[ADD] project/milestones: using project milestones
closes odoo/documentation#15479
Task-id: 3305827
X-original-commit: a0f0953112
Signed-off-by: Xavier Platteau (xpl) <xpl@odoo.com>
Signed-off-by: Zuzanna Luczynska (zulu) <zulu@odoo.com>
This commit is contained in:
committed by
xpl-odoo
parent
4152f67645
commit
bbfe59a659
@@ -156,4 +156,6 @@ You can also create your own buttons to access more specific views:
|
||||
|
||||
project_management/project_dashboard
|
||||
project_management/project_profitability
|
||||
project_management/project_milestones
|
||||
project_management/project_templates
|
||||
|
||||
|
||||
@@ -67,8 +67,8 @@ The following smart buttons are displayed on the top right of the project dashbo
|
||||
Milestones
|
||||
----------
|
||||
|
||||
This section is only visible if :doc:`milestones </applications/sales/sales/invoicing/milestone>`
|
||||
have been enabled in the project you're browsing: go to :guilabel:`Project`, click the
|
||||
This section is only visible if :doc:`milestones <../project_management/project_milestones>` have
|
||||
been enabled in the project you're browsing: go to :guilabel:`Project`, click the
|
||||
:icon:`fa-ellipsis-v` (:guilabel:`vertical ellipsis`) icon on one of your projects, and click on
|
||||
:guilabel:`Settings`. Click on the :guilabel:`Settings` tab, look for :guilabel:`Tasks Management`
|
||||
and make sure :guilabel:`Milestones` is enabled.
|
||||
|
||||
@@ -0,0 +1,67 @@
|
||||
==================
|
||||
Project milestones
|
||||
==================
|
||||
|
||||
**Milestones** enable you to track ongoing project work by designating a sequence of key steps that
|
||||
must be reached before the project’s completion. Milestones are particularly useful in expensive,
|
||||
long, or large-scale projects. They can be used purely for indicative purposes, as a way to ensure
|
||||
that the project is completed in a timely manner.
|
||||
|
||||
Milestones can also be used as a basis for :doc:`invoicing the client </applications/sales/sales/invoicing/milestone>`.
|
||||
This benefits both parties, as it ensures consistent cash flow for project funding and allows the
|
||||
client to pay for the project in several installments.
|
||||
|
||||
Configuration
|
||||
=============
|
||||
|
||||
Enable milestones for the desired project by opening the :guilabel:`Project` app, clicking the
|
||||
:icon:`fa-ellipsis-v` (:guilabel:`vertical ellipsis`) on the project’s card, and clicking
|
||||
:guilabel:`Settings`. Under :guilabel:`Tasks Management`, enable :guilabel:`Milestones`.
|
||||
|
||||
.. note::
|
||||
Milestones are automatically enabled for projects created from a sales order for a service
|
||||
:doc:`invoiced by milestone </applications/sales/sales/invoicing/milestone>`.
|
||||
|
||||
Configure project milestones by clicking the :icon:`fa-ellipsis-v` (:guilabel:`vertical ellipsis`)
|
||||
on the project’s card and selecting :guilabel:`Milestones`. Create a milestone by clicking
|
||||
:guilabel:`New`, entering the milestone's :guilabel:`Name`, selecting a :guilabel:`Deadline` if
|
||||
desired, and clicking :guilabel:`Save`.
|
||||
|
||||
Add or remove options by clicking the :icon:`oi-settings-adjust` :guilabel:`sliders`. The following
|
||||
options are relevant when using
|
||||
:doc:`invoicing based on milestones </applications/sales/sales/invoicing/milestone>`:
|
||||
|
||||
- :guilabel:`Sales Order Item`: this field is filled in automatically with the Sales Order number.
|
||||
- :guilabel:`Quantity (%)`: percentage of the ordered quantity that will automatically be delivered
|
||||
on the sales order once the milestone is marked as reached.
|
||||
|
||||
Once milestones are configured, **you can link project tasks to milestones**. To do so, navigate to
|
||||
the project you created the milestones in, then click one of the tasks to open it. Then, click the
|
||||
:guilabel:`Milestone` field to open a drop-down menu. Select the desired milestone from the list.
|
||||
|
||||
Once all the tasks linked to the milestone are completed (marked as
|
||||
:doc:`Done or Cancelled <../tasks/task_stages_statuses>`), the milestone will be automatically
|
||||
marked as :guilabel:`Reached` in the :menuselection:`Project --> Settings --> Milestones`. You can
|
||||
also check the :guilabel:`Reached` box manually whenever the milestone is reached. Manual checking
|
||||
of the box will not impact the tasks linked to the milestone.
|
||||
|
||||
Using milestones
|
||||
================
|
||||
|
||||
Odoo offers several ways to oversee the project’s milestones and their relationship to ongoing
|
||||
tasks.
|
||||
|
||||
In the **Gantt view**, a milestone is shown as a vertical line marked with a diamond shape,
|
||||
displayed on the day of the milestone’s deadline. The line is color-coded in blue to indicate that
|
||||
the milestone has not yet reached its deadline, or it has been marked as reached (in which case, a
|
||||
check mark is displayed on the milestone). A milestone is color-coded in red if it has not been
|
||||
reached by its deadline.
|
||||
|
||||
If a milestone’s deadline falls on the same day as the project’s deadline, it is displayed with a
|
||||
vertical line marked with a circle, and the same color coding principles as above apply.
|
||||
|
||||
Aside from the Gantt view, you can also create, edit, and mark milestones as reached from
|
||||
:ref:`the project dashboard <project/project-dashboard/milestones>`.
|
||||
|
||||
.. image:: project_milestones/gantt-milestones.png
|
||||
:alt: Project milestones in Gantt view.
|
||||