Delays
|
||||
======
|
||||
|
||||
.. |SO| replace:: :abbr:`SO (sales order)`
|
||||
.. |SOs| replace:: :abbr:`SOs (sales orders)`
|
||||
.. |MO| replace:: :abbr:`MO (manufacturing order)`
|
||||
.. |MOs| replace:: :abbr:`MOs (manufacturing orders)`
|
||||
.. |RfQ| replace:: :abbr:`RfQ (request for quotation)`
|
||||
|
||||
Odoo's *Manufacturing* app displays *delays* in manufacturing orders through the :guilabel:`Delayed
|
||||
Productions` filter. If the |MO|'s end date exceeds its deadline, the deadline is highlighted in red
|
||||
to draw attention to the delay.
|
||||
|
||||
.. image:: delayed/delayed-filter.png
|
||||
:alt: The delayed production filter in Odoo.
|
||||
|
||||
Deadline calculation
|
||||
====================
|
||||
|
||||
The |MO| deadline depends on how the |MO| was created, and is calculated as follows:
|
||||
|
||||
- **Make To Order**: the |MO| deadline is the *Sales Order Delivery Date*.
|
||||
- **Replenishment**: the |MO| deadline is *today + Manufacturing Lead Time*.
|
||||
- **Manually created MO**: the deadline field remains empty.
|
||||
|
||||
.. important::
|
||||
The |MO| *deadline* is not the same as the |MO| *end date*.
|
||||
|
||||
The end date is computed as:
|
||||
|
||||
.. math::
|
||||
\text{End date} =
|
||||
\text{Scheduled start date}
|
||||
+\text{Total duration of all operations}
|
||||
|
||||
Filters
|
||||
=======
|
||||
|
||||
Several additional filters are available to help track delays:
|
||||
|
||||
- :guilabel:`Delayed Productions`: the |MO|'s *scheduled start date* is later than the deadline.
|
||||
- :guilabel:`Late`: the |MO|'s *scheduled end date* exceeds the deadline, highlighted in red.
|
||||
- :guilabel:`Late Availability`: one or more required components are not available before the
|
||||
deadline. For example, a confirmed purchase order or manufacturing order for components is
|
||||
scheduled to end *after* the |MO| deadline.
|
||||
- :guilabel:`Components Available`: all components are available to begin production.
|
||||
|
||||
Use case
|
||||
========
|
||||
|
||||
Consider an |MO| with a deadline of **September 17th**:
|
||||
|
||||
- If production on the |MO| starts after September 17th, it appears in the :guilabel:`Delayed
|
||||
Productions` filter.
|
||||
- If required components are scheduled to arrive after September 17th, the |MO| appears in the
|
||||
:guilabel:`Late Availability` filter.
|
||||
- If the |MO| has a scheduled end date after September 17th, it appears in the :guilabel:`Late`
|
||||
filter.
|
||||
|
||||
.. image:: delayed/deadline.png
|
||||
:alt: An MO with the deadline emphasized.
|
||||
|
||||
By combining these indicators, planners can quickly identify where production is at risk of missing
|
||||
delivery commitments.
|
||||